Application for HT and LT Power Connection
« Back

Details to be furnished by the LT Consumer (duly signed)
  • Single line diagram, signed by contractor and consumer
  • Physical Layout, signed by contractor and consumer
  • Load details, signed by contractor and consumer
  • Insulation reading, signed by contractor and supervisor
  • Earth resistance reading, signed by contractor and supervisor
  • Name of the Contractor
  • Contractor’s License No. with copy of relevant pages
  • Name of the Supervisor
  • Supervisor’s permit no. (attach copy)
  • Metering panel to be provided and shall have
    1. 4P, MCCB with shunt trip
    2. Control fuse and 3 phase terminal block
    3. 3 nos of CT having 5VA, 50-100-200/5A, Cl. 0.5
  • Executing agreement in stamp paper with CSEZ
  • If DG Set is installed, Electrical Inspectorate’s Energisation certificate has to be furnished
  • Relaying of concrete slabs over BIT and removal of used cable drums.
  • The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
Details to be furnished by the HT Consumer & LT Consumers in High Rise Building (duly signed)
Power allocation
  • Set of electrical drawings clearly showing incoming switchgear, metering arrangement etc
  • Application for Power Allocation from CSEZ
  • Name of the Contractor
  • Contractor’s License No. with copy of relevant pages
  • Name of the Supervisor
  • Supervisor’s permit no. with copy
For power connection
  • Executing agreement in stamp paper with CSEZ
  • Set of electrical drawings approved by Electrical Inspectorate
  • A copy of the Safety Certificate issued by Electrical Inspectorate
  • A copy of the completion certificate showing insulation reading of all the equipment, cables, switchgear etc and earth resistance of the installation
  • Test certificate of CT/PT for metering
  • Details of remittance of prepaid energy charges
  • Relaying of concrete slabs over BIT and removal of used cable drums.
  • The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
Details to be furnished by the LT Consumers in High Rise Building (duly signed)
Power allocation
  • Set of electrical drawings clearly showing incoming switchgear, metering arrangement etc
  • Application for Power Allocation from CSEZ
  • Name of the Contractor
  • Contractor’s License No. with copy of relevant pages
  • Name of the Supervisor
  • Supervisor’s permit no. with copy
For power connection
  • Executing agreement in stamp paper with CSEZ
  • Set of electrical drawings approved by Electrical Inspectorate
  • A copy of the Safety Certificate issued by Electrical Inspectorate
  • A copy of the completion certificate showing insulation reading of all the equipment, cables, switchgear etc and earth resistance of the installation
  • Metering panel to be provided and shall have
    1. 4P, MCCB with shunt trip
    2. Control fuse and 3 phase terminal block
    3. 3 nos of CT having 5VA, 50-100-200/5A, Cl. 0.5
Details of remittance of prepaid energy charges
  • Relaying of concrete slabs over BIT and removal of used cable drums.
  • The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
Application Fee : Rs.25 for L.T. and M.V and Rs.1000/- for HT Connection.
 
Download Application for HT and LT Power Connection
 
 
   