| Details to be furnished by the LT Consumer (duly signed) |
- Single line diagram, signed by contractor and consumer
- Physical Layout, signed by contractor and consumer
- Load details, signed by contractor and consumer
- Insulation reading, signed by contractor and supervisor
- Earth resistance reading, signed by contractor and supervisor
- Name of the Contractor
- Contractor’s License No. with copy of relevant pages
- Name of the Supervisor
- Supervisor’s permit no. (attach copy)
- Metering panel to be provided and shall have
|
- 4P, MCCB with shunt trip
- Control fuse and 3 phase terminal block
- 3 nos of CT having 5VA, 50-100-200/5A, Cl. 0.5
|
- Executing agreement in stamp paper with CSEZ
- If DG Set is installed, Electrical Inspectorate’s Energisation certificate has to be furnished
- Relaying of concrete slabs over BIT and removal of used cable drums.
- The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
|
| Details to be furnished by the HT Consumer & LT Consumers in High Rise Building (duly signed) |
Power allocation
|
- Set of electrical drawings clearly showing incoming switchgear, metering arrangement etc
- Application for Power Allocation from CSEZ
- Name of the Contractor
- Contractor’s License No. with copy of relevant pages
- Name of the Supervisor
- Supervisor’s permit no. with copy
|
| For power connection |
- Executing agreement in stamp paper with CSEZ
- Set of electrical drawings approved by Electrical Inspectorate
- A copy of the Safety Certificate issued by Electrical Inspectorate
- A copy of the completion certificate showing insulation reading of all the equipment, cables, switchgear etc and earth resistance of the installation
- Test certificate of CT/PT for metering
- Details of remittance of prepaid energy charges
- Relaying of concrete slabs over BIT and removal of used cable drums.
- The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
|
Details to be furnished by the LT Consumers in High Rise Building (duly signed)
|
| Power allocation |
- Set of electrical drawings clearly showing incoming switchgear, metering arrangement etc
- Application for Power Allocation from CSEZ
- Name of the Contractor
- Contractor’s License No. with copy of relevant pages
- Name of the Supervisor
- Supervisor’s permit no. with copy
|
| For power connection |
- Executing agreement in stamp paper with CSEZ
- Set of electrical drawings approved by Electrical Inspectorate
- A copy of the Safety Certificate issued by Electrical Inspectorate
- A copy of the completion certificate showing insulation reading of all the equipment, cables, switchgear etc and earth resistance of the installation
- Metering panel to be provided and shall have
|
- 4P, MCCB with shunt trip
- Control fuse and 3 phase terminal block
- 3 nos of CT having 5VA, 50-100-200/5A, Cl. 0.5
|
| Details of remittance of prepaid energy charges |
- Relaying of concrete slabs over BIT and removal of used cable drums.
- The laying of the cable through the BIT and under ground will be at your own risk and cost. If the existing live cables/civil structures are damaged, the same after informing this office will have to be rectified at your own risk and cost.
|
| Application Fee : Rs.25 for L.T. and M.V and Rs.1000/- for HT Connection. |
| |
| Download Application for HT and LT Power Connection |
| |