| Sl.No. |
Nature of Application |
Time Limit for disposal |
| 1. |
Proposal for setting up of SEZ/EOU Unit – Automatic Approval |
15 working Days |
| 2. |
Proposal for setting up of SEZ/EOU Unit – Board of Approval |
45 working Days |
| 3. |
To approve change in name of a company or the implementing agency and change from a company to another company |
3 working Days |
| 4. |
To approve merger of two or more Units |
3 Working Days |
| 5. |
To do valuation of software exports declared on Software Export Declaration (SOFTEX) forms; |
3 Working Days |
| 6. |
Grant of eligibility certificates for grant of employment VISA to foreign technicians employed in Special Economic Zone; |
3 Working Days |
| 7. |
Issue of Green Card |
3 Working Days |
| 8. |
Grant of IE Code |
2 Working Days |
| 9. |
DTA Sale in respect of EOU non status holders |
5 Working Days |
| 10. |
Import/Procurement of additional capital goods |
3 Working Days |
| 11. |
Broad Banding/ Diversification |
3 Working Days |
| 12. |
Import of second hand capital goods without age restrictions |
3 Working Days |
| 13. |
Grant/renew Status Holder Certificate provided it does not involve clubbing of FOB value of exports of its parent company in the DTA |
3 Working Days |
| 14. |
Acceptance of Legal Undertaking |
3 Working Days |
| 15. |
De-bonding of Unit – In-principle approval |
15 Working Days |
| 16. |
Re-export/Re-Import permissions |
2 Working Days |
| 17. |
Issue of GSP |
1 Working Days |
| 18. |
Fixation of Input – Output Norms (adhoc) |
45 Working Days |
| 19. |
Fixation of Input – Output Norms – Regular |
90 Working Days |